Outside Remodeling

We’re pleased to announce that the final phase of our storewide remodel will begin very soon!

We’ve been working with Undecorated, the company behind our interior remodeling, to give the outside of our store a fresh new look.

This phase will see the replacement of the fabric awning along 9 mile with translucent polycarbonate supported by a steel roof structure and steel columns.

This structure will wrap around the Garden Center and Grocery Receiving areas, creating a more cohesive modern look as well as better shelter from the elements.

We’ve included some design mockups below, so you can get a better idea of what’s to come.





Tentative Schedule:

  • Demolition on our existing awning, outside columns and structures is slated to begin the week of July 22nd.
  • The outside of the building is to be washed and painted the week of July 29th, with Pier installation* (piers are the foundation for the steel columns that will hold up the roof structure) beginning the week of August 5th.
  • Structural steel installation is slated to begin the week of August 12th.
  • We expect the project to wrap up the week following Labor Day.

These dates are highly contingent on availability of contractors and materials, so please be aware that this timeline could change! We will do our best to keep you updated via social media, our website and in-store postings.

While we’re aware that this process may cause inconvenience in the short term, we’re sure that the results will be worth it!

We would like to thank all of our customers, staff and the Ferndale community for their patience as we improve the look and functionality of our store.